Hursley Road, Toowoomba

  • Hursley Road, Toowoomba Project Image
  • Hursley Road, Toowoomba Project Image
  • Hursley Road, Toowoomba Project Image
  • Hursley Road, Toowoomba Project Image

System

Sewer Pump Station to cater for 453 ET, built to Toowoomba Regional Council specifications

Challenges

Assistance with design of rising main, and configuration to enable the system to be constructed on a small parcel of land.

Solution

QMax Precast Concrete sewer pump station was installed, working with the civil contractor the installation of the concrete structures and connecting services where completed within a week, meaning the site was only disrupted for a very short period of time. The pump station controller was installed and commissioned and the completed system integrated into the TRC Scada network.